Tendering Procedure of Grid Losses for delivery period 2010

According to the specification of the Bundesnetzagentur Amprion GmbH will provide all information in terms of number of lots, amount of energy and structure of each lot three weeks before each tender date at the latest.

The current tender procedures take place on:

  1. 27th of February 2009

  2. 17th of April 2009

  3. 5th of May 2009

  4. 28th of May 2009

  5. 18th of August 2009

  6. 2nd of September 2009

  7. 8th of September 2009

  8. 16th of September 2009

  9. 22nd of September 2009

  10. 28th of September 2009

  11. 12th of October 2009

  12. 27th of October 2009

  13. 3rd of November 2009

  14. 13th of November 2009

The yearly amount of grid losses of Amprion which is procured by tender procedures is structured into particular lots for each delivery period. The amount and structure of each profile may vary between tender dates.

Amprion will provide the profile of each lot three weeks before each tender date at the latest as an Excel-file (e.g. „Profile-Grid-Losses-2010_Part-1.xls“ for the first tender date of the delivery period 2010). In the same manner Amprion will make the individual offer-file (e.g. „2010_TEN_NETLOSSES-P_11XYOUR-EIC-CODE_10XDE-RWENET---W_01.xls“) for each tender date available on the website for download. The letter P within the filename describes the number of each tender (Part). Please find further details concerning the filename within the Excel-File.

The general terms and conditions for tender participation including information concerning products, offer submission and award procedure can be found on our website.

Furthermore please find on our website a draft of the electricity supply contract (Stromliefervertrag) to be used.

A prerequisite for participating in the call for tender process is the existence of a valid balance group or subgroup of the participant in the Amprion control area. Insofar the participant is not a balance responsible entity himself the participant has to bring forward a document in which the balance responsible entity obligates himself to the full extent towards the participant to handle the delivery of the loss energy to Amprion via his balancing group. The delivery has to be carried out according to the balancing group contract concluded between the balance responsible entity and Amprion.

If you have any questions please contact us using the following e-mail address with reference to "Interest tender grid losses":

E-Mail to Amprion

tender date period of submission structure   
of the lot 
average price (€/MWh) maximum price* (€/MWh)
* of the awarded offers
27/02/2009 26/02/2009, 11 a.m. till
27/02/2009, 11 a.m.
Base-Year 44,26 44,30
17/04/2009 16/04/2009, 11 a.m. till
17/04/2009, 11 a.m.
Base-Year 53,50 53,50
05/05/2009 04/05/2009, 11 a.m. till
05/05/2009, 11 a.m.
Base-Year 53,75 53,75
28/05/2009 27/05/2009, 11 a.m. till 
28/05/2009, 11 a.m.
Base-Year 53,56 53,59
18/08/2009 17/08/2009, 11 a.m. till 
18/08/2009, 11 a.m.
Base-Year 51,19 51,19
02/09/2009 01/09/2009, 11 a.m. till 
02/09/2009, 11 a.m.
Base-Year 49,08 49,10
08/09/2009 07/09/2009, 11 a.m. till 
08/09/2009, 11 a.m.
Base-Year 68,65 68,65
16/09/2009 15/09/2009, 11 a.m. till 
16/09/2009, 11 a.m.
Base-Q1 48,61 48,63
22/09/2009 21/09/2009, 11 a.m. till 
22/09/2009, 11 a.m.
Base-Q1 48,63 48,63
28/09/2009 27/09/2009, 11 a.m. till 
28/09/2009, 11 a.m.
Base-Q2 40,73 40,73
12/10/2009 11/10/2009, 11 a.m. till 
12/10/2009, 11 a.m.
Base-Q4 55,04 55,04
27/10/2009 26/10/2009, 11 a.m. till 
27/10/2009, 11 a.m.
Peak-Q2 58,48 58,48
03/11/2009 02/11/2009, 11 a.m. till 
03/11/2009, 11 a.m.
Peak-Q3 64,85 64,85
13/11/2009 12/11/2009, 11 a.m. till 
13/11/2009, 11 a.m.
Peak-Q4 76,80 76,80

Documents for the tender procedure on 02/09/2009

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB)

Documents for the tender procedure on 08/09/2009

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB)

Documents for the tender procedure on 16/09/2009

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 11 KB)

Documents for the tender procedure on 22/09/2009

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 11 KB)

Documents for the tender procedure on 28/09/2009

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB)

Documents for the tender procedure on 12/10/2009

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB)

Documents for the tender procedure on 27/10/2009

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB)

Documents for the tender procedure on 03/11/2009

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB)

Documents for the tender procedure on 13/11/2009

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB)

NB: Amprion reserves the right to amend and update all published information as and when necessary.

The German documents – especially the electricity supply contract – are the legally binding documents. The English documents and the English website are provided for convenience of reading only.

FURTHER INFORMATION

General terms and conditions grid losses (PDF | 25 KB)

Electricity supply contract in German (Stromliefervertrag) for year of delivery: 2010 (PDF | 116 KB)