Re-Injectors

Procedure in the case of connection requests by downstream grid operators for the purpose of feeding into the Amprion grid

Amprion creates the prerequisites for feeding electrical energy from downstream grids into the transmission grid according to the following transparent and non-discriminatory procedure in accordance with §17 EnWG.

A. Overview:

The procedure for the assignment of capacities for feeding in electrical energy from downstream grids encompasses various steps, which are individually explained under B.. The procedure commences upon receipt of a qualified inquiry (B. 1.). This is basically followed by the assignment and preparation of a feasibility study (B. 2.), a capacity commitment (B. 3.) and corresponding contracts (B.4.).

B. Procedure:

1. Qualified enquiry

2. Grid studies

3. Capacity commitment

4. Contractual relationship

5. Dealing with competing grid feed-in requests

6. Scope

7. Reservation regulation

8. Procedure

"Electricity Transmission 2009 and 2013 - Region Model*"

Overview of the expected development of installed power plant capacity and the load flows in the grid areas of German transmission system operators Electricity Transmission 2009 - Region Model* (PDF | 0.4 MB)

Overview of the expected development of installed power plant capacity and the load flows in the grid areas of German transmission system operators Electricity Transmission 2013 - Region Model* (PDF | 0.4 MB)

*The "Electricity Transmission 2009 - Region Model" and "Electricity Transmission 2013 - Region Model" are based on system planning assumptions and are subject to other grid developments. The only assumption is a possible future load and feed-in scenario according to the best skills and abilities. This is why no guarantee can be given for the accuracy and completeness of the information provided and the realization of the scenario described. Moreover, Amprion GmbH reserves the right to change or supplement the information provided.

The use of texts, text parts or graphic material requires the prior consent of Amprion GmbH.

System diagram

A concise presentation of the system diagram can be found in "Electricity Transmission 2009 - Region Model" and "Electricity Transmission 2013 - Region Model" or our company profile. In case of a vested interest, a system diagram with all electricity circuits, switchgears, busbars and substations may be requested from Amprion GmbH under acceptance of a declaration of confidence. For this purpose, please send a letter specifying your vested interest and with a signed declaration of confidence attached to the following address.

Amprion GmbH
Abt. A-AP
Rheinlanddamm 24
44139 Dortmund

Company profile

Declaration of confidence (PDF | 10 KB)

Results

Here you can find an overview of current requests (PDF | 16 KB)