Tendering Procedure of Grid Losses for delivery period 2011

According to the specification of the Bundesnetzagentur Amprion GmbH will provide all information in terms of number of lots, amount of energy and structure of each lot three weeks before each tender date at the latest.

The current tender procedures take place on:

  1. 10th of March 2009

  2. 23rd of April 2009

  3. 6th of May 2009

  4. 2nd of June 2009

  5. 19th of August 2009

  6. 3rd of September 2009

  7. 17th of September 2009

  8. 24th of September 2009

  9. 13th of October 2009

  10. 14th of January 2010

  11. 15th of January 2010

  12. 25th of February 2010

  13. 9th of March 2010

  14. 25th of March 2010

  15. 27th of April 2010

  16. 17th of May 2010

  17. 18th of May 2010

  18. 26th of May 2010

  19. 27th of May 2010

  20. 31st of May 2010

  21. 8th of June 2010

  22. 23th of June 2010

  23. 24th of June 2010

The yearly amount of grid losses of Amprion which is procured by tender procedures is structured into particular lots for each delivery period. The amount and structure of each profile may vary between tender dates.

Amprion will provide the profile of each lot three weeks before each tender date at the latest as an Excel-file (e.g. „Profile-Grid-Losses-2011_Part-1.xls“ for the first tender date of the delivery period 2011). In the same manner Amprion will make the individual offer-file (e.g. „2011_TEN_NETLOSSES-P_11XYOUR-EIC-CODE_10XDE-RWENET---W_01.xls“) for each tender date available on the website for download. The letter P within the filename describes the number of each tender (Part). Please find further details concerning the filename within the Excel-File.

The general terms and conditions for tender participation including information concerning products, offer submission and award procedure can be found on our website.

Furthermore please find on our website a draft of the electricity supply contract (Stromliefervertrag) to be used.

A prerequisite for participating in the call for tender process is the existence of a valid balance group or subgroup of the participant in the Amprion control area. Insofar the participant is not a balance responsible entity himself the participant has to bring forward a document in which the balance responsible entity obligates himself to the full extent towards the participant to handle the delivery of the loss energy to Amprion via his balancing group. The delivery has to be carried out according to the balancing group contract concluded between the balance responsible entity and Amprion. 

If you have any questions please contact us using the following e-mail address with reference to "Interest tender grid losses”:

Amprion

E-Mail to Amprion

tender date period of submission  structure 
of the lot 
average price (€/MWh) maximum price* (€/MWh)
10/03/2009 09/03/2009, 11 a.m.till
10/03/2009, 11 a.m.
Base-Year 50,47 50,50
23/04/2009 22/04/2009, 11 a.m.till
23/04/2009, 11 a.m.
Base-Year 55,82 55,85
06/05/2009 05/05/2009, 11 a.m. till
06/05/2009, 11 a.m.
Base-Year 57,00 57,00
02/06/2009 01/06/2009, 11 a.m. till
02/06/2009, 11 a.m.
Base-Year 58,24 58,25
19/08/2009 18/08/2009, 11 a.m. till
19/08/2009, 11 a.m.
Base-Year 56,34 56,34
03/09/2009 02/09/2009, 11 a.m. till
03/09/2009, 11 a.m.
Base-Year 54,73 54,78
17/09/2009 16/09/2009, 11 a.m. till
17/09/2009, 11 a.m.
Base-Year 53,58 53,58
24/09/2009 23/09/2009, 11 a.m. till
24/09/2009, 11 a.m.
Base-Year 52,21 52,23
13/10/2009 12/10/2009, 11 a.m. till
13/10/2009, 11 a.m.
Peak-Year 78,94 78,94
14/01/2010 13/01/2010, 11 a.m. till
14/01/2010, 11 a.m.
Base-Year 50,64 50,64
15/01/2010 14/01/2010, 11 a.m. till
15/01/2010, 11 a.m.
Peak-Year

68,65

68,65

25/02/2010 24/02/2010, 11 a.m. till
25/02/2010, 11 a.m.
Base-Year 47,69 47,69
09/03/2010 08/03/2010, 11 a.m. till
09/03/2010, 11 a.m.
Base-Year 46,43 46,43
25/03/2010 24/03/2010, 11 a.m. till
25/03/2010, 11 a.m.
Base-Q1 47,79 47,79
27/04/2010 26/04/2010, 11 a.m. till
27/04/2010, 11 a.m.
Base-Q1 54,40 54,55
17/05/2010 16/05/2010, 11 a.m. till
17/05/2010, 11 a.m.
Base-Q3 49,08 49,08
18/05/2010 17/05/2010, 11 a.m. till
18/05/2010, 11 a.m.
Base-Q4 56,52 56,58
26/05/2010 25/05/2010, 11 a.m. till
26/05/2010, 11 a.m.
Peak-Q3 66,00 66,00
27/05/2010 26/05/2010, 11 a.m. till
27/05/2010, 11 a.m.
Peak-Q1 68,50 68,50
31/05/2010 30/05/2010, 11 a.m. till
31/05/2010, 11 a.m.
Peak-Q3 64,75 64,75
08/06/2010 07/06/2010, 11 a.m. till
08/06/2010, 11 a.m.
Base-Q4  58,43  58,65
23/06/2010 22/06/2010, 11 a.m. till
23/06/2010, 11 a.m.
Peak-Q2  61,30  61,50
24/06/2010 23/06/2010, 11 a.m. till
24/06/2010, 11 a.m.
Peak-Q4  76,64  77,26

*) of the awarded offers

Documents for the tender procedure on 03/09/2009

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 9 KB)

Documents for the tender procedure on 17/09/2009

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB)

Documents for the tender procedure on 24/09/2009

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB)

Documents for the tender procedure on 13/10/2009

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB)

Documents for the tender procedure on 14/01/2010

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB)

Documents for the tender procedure on 15/01/2010

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB)

Documents for the tender procedure on 25/02/2010

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB)

Documents for the tender procedure on 09/03/2010

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB)  

Documents for the tender procedure on 25/03/2010

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB)

Documents for the tender procedure on 27/04/2010

Attention: Changes in profile and number of lots

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB)

Documents for the tender procedure on 17/05/2010

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB)

Documents for the tender procedure on 18/05/2010

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB) 

Documents for the tender procedure on 26/05/2010

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB)

Documents for the tender procedure on 27/05/2010

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB) 

Documents for the tender procedure on 31/05/2010

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB)

Documents for the tender procedure on 08/06/2010

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB) 

Documents for the tender procedure on 23/06/2010

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB) 

Documents for the tender procedure on 24/06/2010

Excel-file of the profile (XLS | 1,7 MB)

Offer-file to be used for bidding (ZIP | 10 KB) 

 

NB: Amprion reserves the right to amend and update all published information as and when necessary.

The German documents – especially the electricity supply contract – are the legally binding documents. The English documents and the English website are provided for convenience of reading only.

FURTHER INFORMATION

General terms and conditions grid losses (PDF | 25 KB)

Electricity supply contract in German (Stromliefervertrag) for year of delivery: 2011 (PDF | 116 KB)

back