7. Scope

The procedure described is applicable to qualified connection requests addressed to Amprion as from 30.6.2007. Any connection requests already made before this date, for which no contractual agreements on grid connection have been concluded, have to be migrated to the present procedure.

If contractually secured grid connection capacity is to be increased by more than 5% , the respective party has to go through the entire procedure pursuant to para. B.1. to 4. for all the additional grid capacity required.